Safety audit of Delhi buildings will require 4mn hours or 500K working days, MCD tells Centre
A senior municipal official said that a report on the time and resources required for such a mammoth exercise has been sent to the central government.
Surveying all residential buildings in Delhi for their fire and structural safety – as sought by the Union home ministry last month in light of recent tragedies – would require 4 million man-hours of work. For context on the scale of this task, if a single person spent eight hours every working day inspecting buildings, it would take more than 2,000 years to complete the exercise.

With 500 people deployed exclusively for the task, the preliminary survey alone would take a little over four years, according to estimates submitted by the Municipal Corporation of Delhi (MCD) to the Centre.
To be sure, the survey itself would be followed up with an intensive scientific structural audit of buildings across the Capital, which could cost several lakh rupees per building, according to officials familiar with the matter. The estimates underline the scale of the resources, manpower and technical expertise required to carry out a city-wide assessment.
MCD directed to conduct safety audit
In October, following a series of deadly building collapses in Delhi, the Union ministry of home affairs directed MCD to prepare a roadmap for a city-wide audit of fire and structural safety of every building in the Capital. A senior municipal official said a report detailing the time and resources required for such an exercise has been submitted to the Centre.
“We have submitted that there are more than 40 lakh (4 million) building structures in Delhi. Even if one man assesses a house in one hour, it will require 40 lakh (4 million) working hours, which will translate to 500,000 working days of work. If there are 500 workers deployed for the survey, it will take around 1,000 days. If more people are deployed, the number of days will become proportionally less,” an official said.
Also Read I Co-owner of building which collapsed in Delhi’s Shahdara arrested: Police
The figures of 4 million buildings, 4 million man-hours, 500,000 working days and around 1,000 days with 500 personnel are part of the estimates submitted by the MCD to the Centre. The estimates of the time required in years are HT’s calculations, based on an eight-hour working day and around 250 working days in a year, accounting for weekly offs and gazetted holidays.
On this basis, a single person working full-time on the exercise would take around 2,033 years to survey all the buildings. With 500 people, the 1,000 working days estimated by MCD would translate to a little over four years. This assumes that all 500 personnel spend their entire working day surveying buildings, without being assigned any other responsibilities.
The proposed preliminary exercise would involve filling out a survey form recording details such as the age of a building, its covered area, visible structural deficiencies, and the absence of a fire no-objection certificate (NOC) or building plan. Civic officials said the Centre would have to decide whether such a survey should be conducted and what timeline should be followed.
“Based on the data from this survey, a policy can later be made on how to proceed with this massive problem. The Union government will also decide whether such a survey should be carried out,” one of the officials quoted above said.
The exercise would also entail a substantial salary bill. According to HT’s calculations, deploying 500 junior engineer (JE)-level officials, as one official suggested would be necessary, would cost the civic agency around ₹144 crore in salaries over a little more than four years. A JE earns around ₹60,000 a month, or approximately ₹7.2 lakh annually.
The estimate assumes that all 500 personnel remain deployed for 48 months, with their monthly salaries calculated at the rates cited by officials. If the civic body instead deploys skilled workers, who earn between ₹22,000 and ₹24,000 a month, the salary expenditure would range between ₹52.8 crore and ₹57.6 crore over the same period.
These estimates account only for the salaries of the personnel deployed for the exercise. They do not include auxiliary expenditure such as equipment, paperwork, transportation, administrative arrangements and other logistical requirements, which would add to the overall cost.
Cost of a scientific audit
The above estimates, both for man-hours and salaries, relate only to a preliminary survey that would precede a scientific structural audit. The latter would involve a more detailed technical assessment of buildings and would be more expensive.
According to officials familiar with the matter, a scientific structural audit could cost between ₹1 lakh and ₹5 lakh per building, depending on its size, the second official said, adding that one way to contain costs would be to use the preliminary survey to identify how many buildings actually require a full-fledged structural audit.
Senior officials said the proposal could prove to be a mammoth exercise, requiring substantial funding, manpower and independent technical expertise. Civic agencies currently lack the capacity to inspect millions of buildings.
MCD’s existing annual dangerous-building survey, meanwhile, covers around 3.25 million buildings. It relies largely on visual inspections to flag warning signs such as cracks and leaning walls. The exercise proposed by the home ministry would go further by examining both structural integrity and fire safety.
Also Read I Shahdara building collapse: Special laws gave building on encroached land immunity
The corporation also lacks a dedicated unit specialising in structural safety audits and does not have permanent structural engineers on its rolls. Instead, it relies on 249 empanelled third-party structural engineers. If all 4 million buildings estimated by MCD were to be audited, each engineer would have to assess more than 16,000 buildings.
The home ministry is expected to decide whether MCD should hire a third-party agency or use architects already empanelled with civic bodies.
The challenge of carrying out structural assessments across the Capital is not new. In June 2020, the three erstwhile municipal corporations set a six-month deadline to obtain structural safety certificates for high-risk buildings and older structures that predated the incorporation of seismic provisions in Delhi’s building bye-laws, following the Delhi high court’s intervention. The exercise could barely cover a few thousand buildings even after six years, officials said.
The Tejendra Khanna Committee, set up in 2006 to examine unauthorised construction and misuse of premises, estimated that 70-80% of structures had violated building norms. Delhi also falls under Seismic Zone IV, classified as having a high earthquake risk. Officials said any audit would need to prioritise high-rise buildings, large assembly buildings, government offices, older properties.
ABOUT THE AUTHORParas SinghParas Singh is a New Delhi-based journalist with Hindustan Times, where he serves as Deputy Metro Editor. He reports on urban governance, the Delhi government, the Delhi BJP, water management, the environment, communities and city life. He joined Hindustan Times in 2021 after beginning his journalism career at The Times of India in 2016, where he covered civic bodies, the water and power sectors, and urban infrastructure. Over the last decade, some of his reporting has led to significant public impact, with investigations into environmental violations, corruption and illegal industrial activity contributing to multiple judicial interventions by the National Green Tribunal and the Delhi High Court. A graduate of St. Stephen's College, University of Delhi, Paras studied journalism from the Indian Institute of Mass Communication (IIMC), New Delhi. Having extensively covered the capital's evolving civic and governance landscape, his recent work increasingly explores Delhi's history, built heritage, urban evolution and the relationship between people and place, alongside continuing to report on governance and public policy.Read More